How to install east-west ballast solar mounting system?

2026-02-09 - Leave me a message

[Preparation Before Installation]

Here is a list of items you need to prepare before installation:


Tools:

Screwdriver: Used to firmly tighten screws.

Measuring tape: Used to ensure the bracket is in the correct position.

Level: Used to confirm the bracket is installed horizontally.


Our solar ballast system includes the following accessories:

Pre-assembled Tripod Support、Rail And Rail Splice、Mid Clamp And End Clamp、Rail Clamp、Grounding Clip And Grounding Lug、Ballast Tray、M8*60 Hex Bolts and M8 Flange Nut. It should be noted that you need to provide the cement blocks yourself.


Pre-assembled Tripod Support


East-West Ballast solar mounting bracket

Rail And Rail Splice

Concrete Flat Roof Ballast Solar Mounting SystemEast-West Solar Ballasted Mounting System

Mid Clamp And End Clamp

Solar Flat Roof Mounting SystemEast-West Ballast solar mounting bracket

Rail Clamp

Concrete Flat Roof Ballast Solar Mounting System

Grounding Clip And Grounding Lug

East-West Solar Ballasted Mounting SystemSolar Flat Roof Mounting System

Ballast Tray

East-West Ballast solar mounting bracket



[Step 1]

Unfold the pre-assembled bracket and install M8*60 hex bolts and M8 flange nuts at points A, B, and C marked in the diagram below to secure the tripod bracket.


Concrete Flat Roof Ballast Solar Mounting System



[Step 2]

As per the drawings, the pre-assembled tripod supports in the Solar Flat Roof Mounting System are arranged at 2500 mm intervals.

East-West Solar Ballasted Mounting System



[Step 3]

Place the ballast tray in the pre-assembled tripod support in turn, and the spacing between the two ballast tray is approximately 1275mm, as shown in the figure.


Solar Flat Roof Mounting System



[Step 4]


Place the concrete block on the ballast tray. It should be noted that one pre-assembled tripod support needs to be supported by four concrete blocks, and each concrete block must weigh at least 60 kg. The dimensions and placement of the cement blocks in the Concrete Flat Roof Ballast Solar Mounting System are shown in the following figure.

East-West Ballast solar mounting bracket


[Step 5]

The following is a top view of the pre-assembled tripod support, ballast tray, and concrete block after the above installation steps have been completed.


Concrete Flat Roof Ballast Solar Mounting System



[Step 6]

Connect the rails using the rail splice and fix the rail clamps to the pre-assembled tripod bracket, as shown in the figure.

East-West Solar Ballasted Mounting System


[Step 7]

Place the solar panel on the rail and insert the grounding clip into the bolt of the mid clamp, as shown in the figure.

Solar Flat Roof Mounting System


[Step 8]

Place the solar panels in sequence, and then install the mid clamp and end clamp to secure them,as shown in the figure. This completes the installation of the entire East-West Solar Ballasted Mounting System.

East-West Ballast solar mounting bracketConcrete Flat Roof Ballast Solar Mounting System

[Installation Example]

East-West Solar Ballasted Mounting SystemSolar Flat Roof Mounting SystemEast-West Ballast solar mounting bracket